Enforcement Site plan review and violations

Streck

Cyburbian
Messages
601
Likes
0
Points
18
#1
We have had a few Site Plan development drawings showing previously approved sewer lines that were actually installed outside of their approved utility ROW's. It is apparently not uncommon. It would be very expensive to correct the placements, and usually it does not matter, however we recently had one 10 feet outside of its authorized ROW. This could be costly to future developments if relocation is needed for new building foundations, etc.

Does anyone provide for fines or bonds for utilities found located outside of the ROW in lieu of removal/relocation?
 

arcplans

As Featured in "High Times"
Messages
6,302
Likes
39
Points
23
#3
We have had a few Site Plan development drawings showing previously approved sewer lines that were actually installed outside of their approved utility ROW's. It is apparently not uncommon. It would be very expensive to correct the placements, and usually it does not matter, however we recently had one 10 feet outside of its authorized ROW. This could be costly to future developments if relocation is needed for new building foundations, etc.

Does anyone provide for fines or bonds for utilities found located outside of the ROW in lieu of removal/relocation?
You can't bond after the fact, but you should re-record easements based on where they are.
 

DVD

Cyburbian
Messages
12,891
Likes
49
Points
28
#4
It's either that or the next round of development that digs up the street needs to relocate them. In the mean time follow Raf's advice and fix the easement.
 
Top